- 10 Jul 2017 13:01PDF · -General update
Hindustan Dorr-Oliver Limited has informed the Exchange that as part of Corporate Insolvency Resolution Process (CIRP), looking for potential investors for investment in the Company and management of affairs and submit the Resolution Plan. Accordingly, the company is making enquiries for potential investors and also giving advertisement in the News Papers to this effect.
- 06 May 2017 11:54PDF · -General update
Hindustan Dorr-Oliver Limited has informed the Exchange regarding Initiation of Corporate Insolvency Resolution Process (CIRP) against the Company under the provisions of the Insolvency and Bankruptcy Code 2016 by an order of National Company Law Board (NCLT) with effect from April 21, 2017 and appointment of Mr. Amit Gupta as Interim Resolution Processional.
- 13 Jul 2015 09:45PDF · -General update
Hindustan Dorr-Oliver Limited has submitted to the Exchange a copy of Corrected Financial Results-Segment reporting- for the quarter and year ended March 31, 2015.
- 29 Sept 2014 10:24PDF · -General update
Hindustan Dorr-Oliver Limited has submitted to the Exchange copy of Recast statement of profit and loss for the period from July 01, 2012 to March 31, 2013.
- 04 Aug 2014 19:20General update
Hindustan Dorr-Oliver Limited has informed the Exchange that in accordance with SEBI (Prohobition of Insider Trading Regulation), 1992 the Trading Window will remain closed from August 5, 2014 to August 12, 2014.
- 27 May 2014 14:48General update
Hindustan Dorr-Oliver Limited has informed the Exchange that in accordance with SEBI (Prohibition of Insider Trading Regulations), 1992 the Trading Window will remain closed from May 21, 2014 to May 31, 2014 as the meeting of the Board of Directors of the Company will be held on May 29, 2014 to consider, approve and take on record the Audited Financial Results of the Company for the year ended March 31, 2014.
- 03 Jan 2013 18:34PDF · -General update
Hindustan Dorr-Oliver Limited has informed the Exchange vide letter dated January 03, 2013, that "Hindustan Dorr-Oliver Limited bags order for "Water Soluble Fertilizer Plant & 'D' Train DAP / NPK Plant" in Fertilizer Sector".
- 05 Nov 2012 14:47General update
Hindustan Dorr-Oliver Limited had informed the Exchange that Board of Directors of the Company at its meeting held on August 29, 2012 have appointed Mr. A S Pradha Sarathi as the Company Secretary and Compliance Officer of the Company in place of Ms. Priya Vishwanathan. The Company has now informed the Exchange that Board of Directors of the Company at its meeting held on August 29, 2012, have appointed Mr. A S Pardha Saradhi as the Company Secretary and Compliance Officer of the Company in place of Ms. Priya Vishwanathan. Further, the company has informed the Exchange that Mr.Girish Dave is t
- 05 Sept 2012 13:38PDF · -General update
Hindustan Dorr-Oliver Limited has informed the Exchange vide letter dated September 05, 2012, regarding "Company Petition No.326 of 2012 filed by the Company in the Bombay High Court for a Scheme of Demerger of the Company's manufacturing operations in favour of HDO Technologies Limited (HDOT), wholly owned subsidiary of the Company".
- 18 Jul 2012 11:43PDF · -General update
Hindustan Dorr-Oliver Limited has informed the Exchange vide its letter dated July 17, 2012 that Hindustan Dorr Oliver Limited wins order for "Field Instrumentation Package" for Nuclear Power Projects.
- 03 Apr 2012 20:08PDF · -General update
Hindustan Dorr-Oliver Limited has submitted to the Exchange a copy in terms of Clause 35A of the Listing Agreement regarding Polling results for the Court Convened Meeting held on March 30, 2012.
- 01 Dec 2011 10:06PDF · -General update
Hindustan Dorr-Oliver Limited has informed the Exchange that the Company received recently a prestigious order of the value of Rs.170 Crores from ONGC Petro Additions Limited (OPAL) for entire Effluent Collection and Treatment System (ECTS) Package for its grass root Mega Petrochemical project in the PCPIR / SEZ zone at Dahej. The Project is to be completed in 24 months. ECTS package includes various technology packages from leading Global suppliers for treatment of Petrochemical waste.
- 03 Jun 2011 15:57PDF · -General update
Hindustan Dorr-Oliver Limited has informed the Exchange vide its letter dated June 03, 2011, regarding "Order from Konkola Copper Mines Plc, Zmabia".
- 02 Feb 2010 18:33General update
Hindustan Dorr-Oliver Ltd has informed the Exchange that " The Board of Director at its Meeting held on January 29, 2010 have decided to alter the Objects Clause of the Memorandum of Association of the Company by making a foray into new business of execution of nuclear power plants and the allied activities and deletion of some of the existing sub-clauses and accordingly necessary proposals are being made to the shareholders for alteration in the Object Clause of the Memorandum of Association of the Company."
- 27 Oct 2009 11:26General update
Hindustan Dorr-Oliver Ltd has informed the Exchange that the Company has bagged an order from Anrak Aluminium Limited for detailed engineering, procurement, installation and commissioning work of Residue separation, Washing, Flocculation, Oxalate Removal and Causticisation Package for their upcoming Alumina Refinery of capacity 1.5 MTPA in Vishakhapatnam, Andhra Pradesh. Outotech GmbH, Germany which is a leading global technology provider of process solutions, technologies and services in mining and metallurgical industries is technology partner for the said contract. The combined contract va
- 06 Oct 2009 15:05General update
Hindustan Dorr-Oliver Ltd has informed the Exchange that "The Company has bagged an order from BALCO (a Vedanta Group of Company) worth Rs. 130 Crores for Design, Engineering, procurement, manufacturing, supply, civil works, erection/ construction, testing & commissioning of Fume Treatment plant for their Smelter Expansion Project at Korba. Fives Solios, France a world class expert in this field is the Technology partner for this project. The total order value along with Fives Solios, France is worth Rs. 276 Crores. Execution of the said Project shall be completed within a period of 20 months.
- 29 Jul 2009 14:06General update
Hindustan Dorr-Oliver Ltd has informed the Exchange that the Board of Directors at its Meeting held on July 29, 2009 has decided to foray into new business of execution of nuclear power plants and the allied activities including mining etc. and accordingly necessary proposals are being made to the shareholders for alteration in the Objects Clause of the Memorandum of Association of the Company.
- 17 Jul 2009 18:51General update
Hindustan Dorr-Oliver Ltd had informed the Exchange regarding appointment of Mr. Ashok Kumar Basu as an Additional Director on the Board of the Company. Further the Company has now informed the Exchange that his Directorship will take effect from September 01, 2009 as desired by him.
- 06 Jul 2009 10:41General update
Hindustan Dorr-Oliver Ltd has informed the Exchange that: "HDO has bagged an order from CIDCO (City & Industrial Corporation of Maharashtra Ltd.), Navi Mumbai, for Design, Engineering, Supply, Construction, Erection and Commissioning of their 70 MLD Sewage Treatment Plant coming up in Kharghar, Navi Mumbai. The project value is 60.3 crores and completion period is 24 months. This is repeat order from same customer in past 2 years. The project also includes 5 year Operation and Maintenance. HDO will be installing state-of-the-art Sequential Batch Reactor Technology for treatment of Sewage".
- 29 Jun 2009 10:15General update
Hindustan Dorr-Oliver Ltd has informed the Exchange that "The Company has bagged another order worth Rs. 108.9 Crores from HPCL - Mittal Energy Limited for Effluent Treatment Plant of 12 MLD capacity to be executed within a period of 17 months. HDO will integrate all concurrent innovative technologies like SBR, MBR, Sludge Bio-remediation and VOC treatment to ensure zero discharge and pollution free refinery, meeting international standards. By securing this order, the complete water management solution for this new grass root refinery will be executed by HDO. In addition to the above, HDO has
- 22 Jun 2009 16:48General update
Hindustan Dorr-Oliver Ltd has informed the Exchange that: "The Company has bagged a prestigious project worth Rs.53.05 crores from HPCL-Mittal Energy Limited for Raw Water Treatment Plant of Capacity 130 MLD. This project will be executed on Turnkey basis and completion period is 14 months. Further, Engineers India Ltd. will be the Project Management Consultants for the subject contract."
- 15 Jun 2009 09:37General update
Hindustan Dorr-Oliver Ltd has informed the Exchange that the Company has bagged a prestigious project worth Rs. 126.95 crores from HPCL- Mittal Energy Limited for RO based DM plant of capacity 21 MLD. This will be executed on Turnkey basis on High Efficiency Reverse Osmosis technology. This Project will bring in additional qualification in HDO. Engineers India Ltd. will be the Project Management Consultants for the subject contract. Execution of the said project shall be completed within a period of 13 months.
- 25 May 2009 11:11General update
Hindustan Dorr-Oliver Ltd has informed the Exchange that "The Company has bagged an order from National Aluminium Corporation Limited valued at Rs.24.5 crores for their Phase II expansion project at Alumina Refinery, Damanjodi, Orissa. This civil and structural contract involves PCC & RCC works for sub structure/super structure in substation/control station including structural steel fabrication and erection work for tankages, piperack, lifts, and cable trays etc. of this project. Execution of the said project shall be completed with a period of six (6) months".
- 08 Apr 2009 09:51General update
Hindustan Dorr-Oliver Ltd has informed the Exchange that the Company has bagged two prestigious Orders in Mineral Sector worth Rs. 66 crores from Vedanta Group. HDO was awarded an order worth Rs.48.5 crores for their 12.5 LTPA Aluminium Smelter Expansion Project at Jharsuguda. The scope involves Manufacturing, Procurement, Supply, Civil Works, Material Handling, Erection, Commissioning, Integration of Air-Water Piping System. Execution of this project shall be completed within 12 months period. HDO has also received an order worth Rs.17.5 crores from Vedanta Group for their Milk of Lime Plan
- 02 Mar 2009 10:42General update
Hindustan Dorr-Oliver Ltd has informed the Exchange that "The Company has bagged an order worth Rs. 24.00 crores from M/s. HPCL-Mittal Energy Ltd. for detailed engineering, shop & site fabrication, transportation and supply of Process Pressure Vessels weighing from 50 MT to 25O MT each. Execution of the said project shall be completed within a period of 12 to 14 months."
- 25 Feb 2009 11:03General update
Hindustan Dorr-Oliver Ltd has informed the Exchange that: "The Company has bagged a prestigious order for Uranium Ore Processing Plant from Uranium Corporation of India Ltd.(UCIL) worth Rs. 441 crores for their Greenfiled Ore Mining and Processing facility of capacity 3000 MTPD coming up at Tumalapalle in Andhra Pradesh on LSTK basis. The process plant shall adopt innovative Alkali Pressure Leaching process technology which will be used in India for the first time and M/s Bateman of South Africa are Company's Technology partners for this project. Execution of the above project shall be complet
- 26 May 2008 13:33General update
Hindustan Dorr-Oliver Ltd has informed the Exchange that: "The Company has got an order from Vedanta Aluminium Ltd. worth Rs.250 crores for Design, Engineering, procurement, manufacture, supply, civil works, erection/construction, testing, commissioning and performance guarantee tests of Settler & Washer Package alongwith associated facilities for expansion of their 3 MMTPA Alumina Refinery Project at Lanjigarh, Orissa, India. FLSMIDTH Dorr-Oliver Eimco Gmbh, Germany are Company's Technology partners for the project. Execution of the said project shall be completed within a period of seventeen